TESTKING C-TS422-2023 LEARNING MATERIALS, C-TS422-2023 VALID EXAM VCE FREE

Testking C-TS422-2023 Learning Materials, C-TS422-2023 Valid Exam Vce Free

Testking C-TS422-2023 Learning Materials, C-TS422-2023 Valid Exam Vce Free

Blog Article

Tags: Testking C-TS422-2023 Learning Materials, C-TS422-2023 Valid Exam Vce Free, Valid C-TS422-2023 Exam Topics, C-TS422-2023 Relevant Exam Dumps, Valid C-TS422-2023 Learning Materials

The clients can consult our online customer service before and after they buy our C-TS422-2023 useful test guide. We provide considerate customer service to the clients. Before the clients buy our C-TS422-2023 cram training materials they can consult our online customer service personnel about the products' version and price and then decide whether to buy them or not. After the clients buy the C-TS422-2023 Study Tool they can consult our online customer service about how to use them and the problems which occur during the process of using. We will help you pass the C-TS422-2023 exam in the shortest time.

SAP C-TS422-2023 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Lean Manufacturing in SAP S
  • 4HANA: This section covers repetitive manufacturing master data, line load planning, and Kanban systems.
Topic 2
  • Material Requirements Planning in SAP S
  • 4HANA: This part of the exam covers an examination of planning strategies, tools, and long-term planning concepts. Overview of MRP fundamentals and lot size procedures.
Topic 3
  • Process Orders in SAP S
  • 4HANA: This section covers an introduction to process order components, processing, and relevant master data objects. Overview of Good Manufacturing Practices (GMP) features.
Topic 4
  • Advanced Planning in SAP S
  • 4HANA: This section includes an overview of advanced planning fundamentals and master data. Explanation of key tools and processes. Discussion of planning evaluation concepts.
Topic 5
  • Introduction to SAP S
  • 4HANA Supply Chain Planning: This part covers the background and motivation for SAP S
  • 4HANA, its main components, business applications, and user experience strategy.
Topic 6
  • Capacity Planning in SAP S
  • 4HANA: This section covers a discussion of SAP S
  • 4HANA best practices, SAP HANA database concept, SAP Fiori user experience, and embedded analytics capabilities.
Topic 7
  • Introduction to SAP S
  • 4HANA Production Planning: This section covers an overview of production planning components, functions, and planning approaches. Exploration of emerging trends.
Topic 8
  • Master Data in SAP S
  • 4HANA: This section covers the exploration of crucial production-related master data elements, with emphasis on bill of material, routing, and production version.

>> Testking C-TS422-2023 Learning Materials <<

C-TS422-2023 Valid Exam Vce Free - Valid C-TS422-2023 Exam Topics

Easy4Engine C-TS422-2023 practice test simulates the real SAP C-TS422-2023 exam environment. This situation boosts the candidate's performance and enhances their confidence. After attempting the C-TS422-2023 practice exams, candidates become more familiar with a real SAP S/4HANA Cloud Private Edition - Production Planning and Manufacturing C-TS422-2023 Exam environment and develop the stamina to sit for several hours consecutively to complete the C-TS422-2023 exam. This way, the actual SAP S/4HANA Cloud Private Edition - Production Planning and Manufacturing C-TS422-2023 exam becomes much easier for them to handle.

SAP S/4HANA Cloud Private Edition - Production Planning and Manufacturing Sample Questions (Q24-Q29):

NEW QUESTION # 24
Which of the following are features of the clean core dashboard? Note: There are 2 correct answers to this question.

  • A. Customers can use the dashboard in the dev test production tenants.
  • B. It can be used in all SAP S/4HANA Cloud editions.
  • C. Customers can grant access to the dashboard to partners.
  • D. It can be accessed by using SAP For Me.

Answer: C,D


NEW QUESTION # 25
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

  • A. To reduce the number of changes required in bills of material
  • B. To make the assignment of components easier
  • C. To increase the number of planning levels
  • D. To simplify the structure of bills of material
  • E. To reduce the number of material masters

Answer: B,D,E

Explanation:
Phantom assemblies are assemblies that have their own product structure, but whose assembly does not actually physically exist. The components of the phantom assembly are incorporated directly in the superordinate product. The product structure of the superordinate product contains a reference to the phantom assembly. You can use phantom assemblies for the following purposes:
To simplify the structure of bills of material: Phantom assemblies allow you to group components that belong together logically or functionally, without creating an additional level in the product structure. This can make the product structure easier to maintain and understand.
To reduce the number of material masters: Phantom assemblies do not require a material master record in SAP S/4HANA, as they are not physically produced or stored. This can save storage space and reduce the effort of creating and updating material masters.
To reduce the number of changes required in bills of material: Phantom assemblies can be used to represent common subassemblies that are used in multiple products. This way, you only need to maintain the product structure of the phantom assembly once, and any changes will be reflected in all the products that reference it.
Phantom assemblies do not increase the number of planning levels, as they are not considered as separate planning objects. They also do not make the assignment of components easier, as the components are assigned to the superordinate product, not to the phantom assembly. Reference: Phantom Assembly | SAP Help Portal, Phantom Assembly | SAP Help Portal, Planning Phantom Assemblies | SAP Help Portal.


NEW QUESTION # 26
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.

  • A. Material type
  • B. Procurement type
  • C. MRP group
  • D. MRP type

Answer: A,B

Explanation:
In SAP S/4HANA, MRP determines whether to createplanned orders(for in-house production) orpurchase requisitions(for external procurement) based on specific master data settings in the material master. The procurement type(A), maintained in the MRP 2 view (field: ProcurementType), is a key determinant. For example, procurement type "E" (In-house production) triggers planned orders, while "F" (External procurement) generates purchase requisitions, and "X" (Both) allows MRP to decide based on additional settings like quotas.
Thematerial type(B), defined during material creation and linked to configuration (Logistics - General > Material Master > Basic Settings > Define Material Types), also influences this decision indirectly. For instance, material types like "FERT" (Finished Goods) are typically produced in-house, favoring planned orders, while "ROH" (Raw Materials) are procured externally, favoring purchase requisitions.MRP type(C) controls whether MRP runs (e.g., "PD" for MRP planning), but it does not directly determine the order type.
MRP group(D) groups materials for planning parameters but does not directly dictate planned orders versus purchase requisitions.


NEW QUESTION # 27
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note:
There are 2 correct answers to this question.

  • A. Routing
  • B. Production version
  • C. Production cost collector
  • D. Repetitive manufacturing profile

Answer: A,B

Explanation:
In SAP S/4HANA repetitive manufacturing, the production line is represented by a work center, and this is maintained in:
* Production version(B): The production version (material master, MRP 4 view, transaction C223) links a material to a specific production line by referencing a work center (via the routing or rate routing).
The "Production Line" field explicitly identifies the work center used for repetitive production, tying it to the planning table (MF50).
* Routing(D): In repetitive manufacturing, a rate routing (transaction CA21) or standard routing (CA01) defines the operations and assigns the work center (field: Work Center) thatrepresents the production line. This work center is then referenced in the production version for planning and execution.
Production cost collector(A) (transaction KKF6N) collects costs for repetitive production but doesn't define the work center-it uses the production version's data.Repetitive manufacturing profile(C) (Customizing, transaction OSP2) controls REM settings (e.g., backflushing), not the specific work center assignment. This is per SAP's REM master data setup.


NEW QUESTION # 28
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

  • A. Assign the overall profile to the authorization profile.
  • B. Assign the alert profile to the overall profile.
  • C. Create an object selection variant for alerts according to the priority of ATP categories.
  • D. Create an object selection variant for productionplanningrelated alerts.

Answer: B,D


NEW QUESTION # 29
......

You must be attracted by the APP online version of our C-TS422-2023 exam questions, which is unlike other exam materials that are available on the market, study torrent specially proposed different version to allow you to learn not on paper, but to use on all kinds of eletronic devices such as IPAD, mobile phones or laptop to learn. This greatly improves the students' availability of fragmented time. You can also have a quite enjoyable experience with APP online version of our C-TS422-2023 Study Materials. Just have a try on this version of our C-TS422-2023 learning guide!

C-TS422-2023 Valid Exam Vce Free: https://www.easy4engine.com/C-TS422-2023-test-engine.html